On April 10, Phase I of the 200 MW Wind Power Project in Block B of the sixth wind farm in Anbei, Gansu Province was connected to the grid with a full capacity of 100 MW.
After approval in 2021, the project completed part of the hoisting work in February 2022, pre-connection acceptance by the provincial power grid company in March, and all grid connection tasks in April. The excellent cooperation of all construction personnel has laid a solid foundation for the success of grid connection.